EXPERTISE · CONSTRUCTION PLANNING

Construction Organization Plan

A Construction Organization Plan (POS) brings the site layout, temporary facilities, traffic, utilities and safety measures into a coordinated construction scenario.

STMK design team

Concept diagram · not to scaleSite boundary / traffic route / lifting zone

0:00 / 0:31

A short visual guide to the site plan. Silent video · 31 seconds.
DESIGN PREPARATION

What is a POS?

Its central drawing is the construction site plan. It coordinates the permanent building with temporary roads, facilities, cranes, hazard zones and utility routes so that the team can organise the site before work begins.

01 / ПОС

Site boundaries and facilities

Boundaries and fencing

The site plan records the work-zone boundary, fence type and height, post construction, support spacing and safe pedestrian routes.

Temporary site facilities

It locates temporary cabins, the canteen and site office together with their dimensions, areas and utility connections.

Site arrangement
Site arrangementOpen drawing ↗
02 / ПОС

Movement and lifting operations

Cranes and hazard zones

It defines the crane position, working radius, outrigger footprint and the boundaries of lifting and falling-load hazard zones.

Roads and movement

It sets internal-road widths, turning radii, gates, traffic direction and the wheel-wash point at the exit.

Plant operating zones
Plant operating zonesOpen drawing ↗
03 / ПОС

Infrastructure and storage

Storage and work areas

It assigns material storage, a concrete-pump standing area with mixer positions and a segregated temporary waste area.

Temporary utilities

It maps electrical intake points, distribution boards, temporary water and drainage routes, sanitary facilities and site lighting.

Temporary infrastructure
Temporary infrastructureOpen drawing ↗
04 / ПОС

Temporary works and safety

Road slabs and excavation

It defines temporary-road slab zones and quantities, the excavation boundary, protection system, warning barriers and signs.

Safety and key quantities

It records hydrants and fire points together with building footprint, temporary-building area and total temporary-road length.

Roads and logistics
Roads and logisticsOpen drawing ↗

Anonymised working fragments: identifying details and source metadata have been removed. Only flattened web images are published.

Before issuing the plan

  1. Coordinate site boundaries and fencing
  2. Check traffic routes and turning radii
  3. Define cranes and hazard zones
  4. Route temporary utilities and lighting
  5. Assign storage, waste and concrete-pump areas
  6. Record fire-safety points and temporary-work quantities